fbpx
Today’s LiveWire Spotlight addresses PRC-024-1 Draft 6, the only remaining standard under Project 2009-07 “Generator Verification” to not receive sufficient industry support in the balloting process – only 60.5% in the last vote. The standard consists of four requirements and two attachments specifying the operating thresholds of “no-trip” zones – generator voltage and frequency protective relays must not react to external transients within those limits.